We continue our journey through the renovation process at the Samuel Noakes House at 101 West Cork Street/201 South Braddock Street. Updates are posted each Tuesday through the PHW blog, following the progress with virtual hardhat tours.
The previous entries may be found at the PHW blog at part 1, part 2, part 3, part 4, part 5, part 6, part 7, part 8, part 9, part 10, part 11, part 12, part 13, part 14, and part 15.
Although it has been a while since we last checked into the Noakes project, work is ongoing at the house. The project is starting to wind down to the cosmetic touches, but we’ll have a few more updates on the house before the work is completely finished. This time, enjoy some images of the new meter stack installation, some concrete work, and interior wiring installations.
The meter stack is moved to its new location
Concrete work continues around to the side and underneath the house
Interior wiring for networking is installed
Electrical wiring goes in too
Another look at some of the new wiring installations in the Cork Street side